How to Create a Project Schedule
Complete guide to schedule creation and management for construction project managers
The Schedule Module helps you create and manage project timelines using three flexible methods: importing existing schedules, using pre-built templates, or building activities manually. Choose the method that best fits your project setup and existing documentation.
Before you start:
- Ensure you have project access in Mastt
- For imports: Prepare your .xml (MS Project) or .xer (Primavera P6) files
Steps
Access the Schedule Module
- Navigate to your project
- Using the navigation toolbar, click Schedule Module
Method 1: Import Schedule
- Drag and drop your schedule file into the upload area, or click to browse
- Select your file type:
- MS Project: Use .xml files
- Primavera P6: Use .xer files
- Click Import
- Review the imported milestones and activities in the preview
- Click Import to confirm when satisfied with the data
- Click Save to finalize the imported schedule
Overwrite Existing Schedule
You can easily update your schedule by uploading a new one and choosing to overwrite the existing schedule.
- From the Schedule module, click the Import button
- Choose the file type and upload your new schedule file
- When prompted, confirm if you want to overwrite the existing schedule
Method 2: Use Schedule Template
- Click Use Templates
- Choose between:
- Standard Project Template
- Standard Construction Template
- Select your project start date
- Click Import Template
- Review and customize the template activities as needed
- Click Save when finished
Method 3: Create Activities Manually
- Click + Activity
- Complete the activity details:
- Activity name
- Project phases
- Status
- Start date
- Baseline completion date
- Planned completion date
- Tasks
- Comments (Save activity first to add comments)
- Toggle Start of Project if this activity marks project commencement
- Toggle Completion if this activity marks project completion for tracking
- Select an activity icon if desired
- Click Save
- Repeat steps for additional activities using + Add Activity
Edit Individual Activities
- Click the activity you want to edit
- A form will appear on the right-hand side of your schedule page
- Make the necessary edits to the activity details
- Click Save when completed
Reorder Activities:
- Click and hold on the grab bar and drag the activity to the desired position
- Click Save to confirm the changes.
Delete Individual Activities
- Locate the activity you want to delete
- Click the Delete icon for that activity
- A dialog box will open
- Click Delete Activity to confirm and proceed
Bulk Edit
- Use checkboxes to select activities you want to move forward or back
- Click Bulk Edit
- Select your action (Move Dates, Status, Set Phase, Delete, you can also use Select all or Unselect All)
- Customize the form to match your required changes
- Click Save to apply all changes
Troubleshooting
- Problem: Import fails with file error. Solution: Ensure your file is in .xml (MS Project) or .xer (Primavera P6) format and not corrupted
- Problem: The Template doesn't match the project needs. Solution: Import the closest template, then manually add or remove activities as required