Adjusting Budgets and Sub-Budgets
Move funds between budgets or tweak amounts to fit project shifts, risks, or scope changes - all while keeping finances on track.
Table of Contents
Key Concepts
- Budget Transfer: Moving funds from one budget to another (e.g., from Risk Provision to Contractor Budget)
- Budget Adjustment: Adding or removing funds from a single budget
- Draft Status: Changes are saved but not applied to actual budgets
- Approved Status: Changes are active and reflected in budget totals
Step-by-Step Guide
Transfer Funds Between Budgets
- Navigate to the Cost Module via the side menu
- Select Budgets > Adjustments
- Click the Transfer Funds button
- Complete the transfer details:
- Enter a descriptive title (e.g., "Risk Transfer for Variation #123")
- Select the source budget in From Budget
- Enter the transfer amount
- Select the destination in To Budget
- Set the status (Draft or Approved)
- Upload any supporting documentation if required
- Click Add to complete the transfer
Add or Remove Funds from a Budget
- Navigate to the Cost Module via the side menu
- Select Budgets > Adjustments
- Click the Add/Remove Funds button
- Fill in the adjustment details:
- Enter a descriptive title
- Select the Target Budget
- Enter a positive amount to add funds or negative amount to remove funds
- Set the status (Draft or Approved)
- Upload any supporting documentation if required
- Click Submit to complete the adjustment
Modify Existing Adjustments
- Navigate to Cost > Budgets > Adjustments
- Locate the adjustment you want to modify
- Click the Actions button and select Edit
- Update the necessary fields
- Click Update to save changes
Delete Adjustments
- Navigate to Cost > Budgets > Adjustments
- Locate the adjustment you want to remove
- Click the Actions button and select Delete
- Confirm deletion in the popup dialog
Best Practices
- Use descriptive titles that reference the reason for the adjustment
- Keep adjustments in Draft status until you've verified all details
- Document the reason for significant budget changes
- Review all affected budgets after making adjustments
- Maintain an audit trail by uploading relevant supporting documents
Troubleshooting
Adjustment Not Reflecting
- Symptom: Budget totals haven't updated
- Cause: Adjustment still in Draft status
- Solution: Change status to Approved
Last Updated: February 21, 2025