Activity Slip and Gain: Tracking Schedule Performance
Activity Slip and Gain helps you quickly see how your project/program activities are performing against expected completion dates and identify specific activities that have contributed to project/program delays. This feature provides visual indicators that highlight schedule variances, allowing you to proactively manage timeline risks.
Key Concepts
Baseline Dates: The original expected completion dates for activities, established at the start of a project.
Forecast/Planned Dates: The updated expected completion dates based on current information from consultants and contractors.
Actual Dates: The dates when activities are actually completed.
Slip: When an activity is expected to be completed later than the baseline date (shown in red).
Gain: When an activity is expected to be completed earlier than the baseline date (shown in green).
Step-by-Step Guide
Step 1: Setting Baseline Dates
- Navigate to the Project Schedule section
- Select the activities you want to baseline
- Set baseline dates for each activity
Note: Baseline dates establish the foundation for tracking schedule performance.
Step 2: Updating Forecast/Planned Dates
- Open your project schedule
- Select the activity requiring a date update
- Enter the new forecast/planned date based on current information
- Save your changes
Note: As you receive updates from consultants and contractors, regularly update the forecast dates.
Step 3: Viewing Slip and Gain Indicators
- Navigate to the Project Schedule section
- Look for the visual indicators on the Schedule Worm Chart:
- Red indicators show activities slipping behind schedule
- Green indicators show activities ahead of schedule
- Note the delta values (days ahead or behind) for each activity
Best Practices
- Set realistic baseline dates at the project start
- Update forecast dates promptly when you receive new information
- Pay special attention to activities on the critical path
- Use slip indicators to identify areas needing intervention
- Document reasons for significant slips or gains
Troubleshooting
Incorrect Slip/Gain Calculations
- Symptom: Slip/gain values don't match your expectations
- Cause: Incorrect baseline or forecast dates
- Solution: Verify that both baseline and forecast dates are entered correctly
Missing Visual Indicators
- Symptom: No red or green indicators appear
- Cause: Baseline dates may not be set
- Solution: Ensure baseline dates are established for all activities
Note: Changes to the project scope may require re-baselining the schedule to ensure accurate slip and gain tracking.
Last Updated: March 21, 2025