Using the Audit Log and Advanced Features in Mastt
Mastt offers advanced features including the Audit Log for tracking all changes made in your project, Snapshots for capturing project data at specific points in time, and Project Settings for customizing your project configuration. These tools enhance accountability, reporting, and project personalization.
Objective
By the end of this guide, you'll be able to:
- Use the Audit Log to track changes and maintain accountability
- Create and utilize project Snapshots for reporting and historical comparison
- Configure Project Settings to customize your project environment
Prerequisites
- Access to a Mastt project
- Basic understanding of Mastt modules
- Appropriate permissions for accessing advanced features
Video Walkthrough
Step-by-Step Guide to Advanced Features
Using the Audit Log
1. Understanding the Audit Log- The Audit Log tracks who made any change in the system
- It provides accountability and transparency
- Access it from the sidebar navigation
- Search for a specific record by entering search terms
- Filter by record type:
-
- Adjustments
- Budget
- Cash Flow
- Contract
- Forecast
- Payment
- Variation
- Set custom date ranges to narrow your search
- Use preset date options or define your own range
- Default view shows the most recent month
- Each entry shows:
- What was changed
- Who made the change
- When the change occurred
- Details of the change
Creating and Using Snapshots
1. Understanding Snapshots- Snapshots preserve a copy of your project at a specific point in time
- They're useful for:
- Creating period-end reports
- Comparing project status over time
- Preserving historical data
- Navigate to the Snapshots module from the sidebar navigation
- Click + Take Snapshot
- Enter a title for the snapshot (e.g., "Report May 2025")
- Set the Current as of date
- This doesn't affect the data captured
- It's for reporting purposes only
- Click on a snapshot name to open it in a new tab
- The interface changes to orange to indicate you're in a snapshot
- Changes made in snapshots don't affect the live project
- Changes in the live project don't affect existing snapshots
- Click Back in the top left corner to return to the Snapshots list
- Or simply close the snapshot tab to return to your project
- Snapshots open in new tabs for easy comparison
Configuring Project Settings
1. Accessing Project Settings- Click on Settings at the bottom of the sidebar navigation
- This opens the Project Settings form
- Click on the Name and Photo tab
- Enter a new name if needed
- Click Upload Image and select a photo
- Click Save to apply changes
- Navigate to the Project Information tab
- Verify your workspace (organization) is correct
- Enter or update the project number if needed
- Add or modify the point of contact information
- Click Save to store your changes
- Select the Location tab
- Enter the latitude and longitude manually, or
- Type the address in the search field to auto-populate the latitude and longitude fields.
- Click Save to confirm the location
- Go to the Brand tab
- To upload a client logo, click Upload Image under Client Logo (available to project admins and workspace admins)
- To upload a workspace logo, click Upload Image under Workspace Logo (available to workspace admins only)
- Select your preferred font style from the dropdown options
- Click Save to apply your branding preferences
- Click on the User Management tab
- Add users from different workspaces as needed, or
- Invite new users without existing Mastt accounts if required
Refer to the How to Add a User to a Project for a detailed guide
- If you have custom columns configured with Mastt Support
- They will appear here for project-by-project configuration
Contact Mastt support to request additions or deletions of custom columns
Common Pitfalls and Solutions
- Issue: Can't find specific changes in Audit Log
- Solution: Refine your search terms or adjust the date range
- Issue: Snapshot showing incorrect data
- Solution: Ensure you create snapshots at the appropriate time
- Issue: Unable to see certain settings
- Solution: Some settings require administrator permissions
- Issue: Changes in snapshots are not saving
- Solution: Remember, snapshots are independent of the live project
Next Steps
Now that you understand Mastt's advanced features, explore the Program Management guide to learn how to manage multiple projects within a program structure.
Note: Regular use of snapshots at key project milestones or reporting periods creates a valuable historical record of your project's progress and facilitates more meaningful reporting.