How to Return Retention and Generate a Release Certificate

Complete guide to releasing held retention funds and generating release certificates in Mastt

Returning retention releases previously held funds to contractors once contract conditions are met. This guide shows you how to create a retention return payment and generate a release certificate in Mastt.

Before you start

  • A contract with held retention exists in your project.
  • You know the retention amount to release.

Create a retention return payment

  1. Go to the Cost module.
  2. Click Payments.
  3. Click + Add Payment.
  4. Enter a descriptive name in the Title field (for example, "Retention Release — Final Payment").
  5. Select the Payment Date.
  6. Set the Payment Status to Paid.
  7. Select the Cash Flow Month.
  8. Click + Add Contract and select the contract that the retention return applies to.

Enter the negative retention amount

Note: Positive amounts hold funds. Negative amounts release funds. Always use the Retained This Payment field for retention returns. Do not use the Percentage field.

  1. Go to the Retention section and click to expand it.
  2. Click the Retained This Payment field.
  3. Enter a negative amount (for example, -5000 to return $5,000).

Payment Retention section with -5,000.00 entered in the Retained This Payment field and 0 in the This % field

Complete the payment

  1. Make sure the retention amount displays as a negative value.
  2. Check the overall payment total.
  3. Click Add to save the payment.

Note: The retention breakdown appears only on payment letters.

Generate a release certificate

  1. Go to the Cost module.
  2. Click Payments.
  3. Click the retention return payment in the Payments register.
  4. Click Actions.
  5. Select one of the following options:
    • Payment Certificate to generate the default certificate.
    • A PDF template to generate a customized release certificate.

Payment actions menu with Edit Payment, Payment Certificate, Payment Schedule and Final Payment Certificate options

Troubleshooting and FAQs

Can I release only part of the retention?

Yes. Enter a negative amount for the portion you want to release (for example, -$25,000 when returning part of $50,000 held). You can create additional retention return payments for future releases.

Do I need a separate payment for each contract?

Yes. Each retention return payment must be linked to a specific contract. Create a separate payment for each contract that requires a retention release.

What is the difference between the Retained This Payment field and the Percentage field?

For retention release, always use the Retained This Payment field to enter your negative dollar amount. The Percentage field is not used for retention release.

Why does my retention release show 0%?

If your payment only contains a retention release with no other claimed amounts or line items, the Percentage field will display as 0%. This is expected. The percentage is calculated against the payment total, and with no other amounts in the payment, there is no base to calculate from. The retention dollar amount is still correct and the release will process normally.

Need help?

Contact Mastt Support for additional assistance with retention management.