How to View and Manage Change Orders in Change Order Overview

Complete guide to navigating Change Order Overview for construction project managers

Change Order Overview is your central hub for managing a change order in Mastt. From here, you can review change order details and approval status, view cost allocations, assess time impacts, manage supporting documents, and track change order history, all in one place.

Before you start

A change order must already exist within a contract before you can view Change Order Overview.

Open Change Order Overview

  1. From the Mastt Home page, click a project tile to open your project.
  2. Click Cost in the left navigation bar.
  3. Click Changes in the top navigation bar to open the Changes register.
  4. Click the change title to open Change Order Overview.

Find your way around the tabs

Change Order Overview organizes change order information across five tabs.

TabWhat it shows
ChangeThe default view. Core details of the change order, including classification, approval status, and administrative fields.
AmountsA detailed breakdown of all cost allocations included in the change order.
Time ImpactHow the change order affects the project schedule.
DocumentsAll documents related to the change order.
Audit LogA complete read-only history of all changes made to the change order, including user activity and timestamps, so you can track who made changes and when.

Change tab

Tip: Click the Contract Name below the change title to go directly to the Contract Overview page.

SectionWhat it shows
OverviewThe Vendor, Change Category, and Contract Change Number assigned to the change order
DatesKey dates, including Date Received, Date Approved, and Approved By
Additional FieldsReference and tracking numbers such as Change Number, Reference Number, Change Approval Number, Clause, and other details
RecommendationThe recommendation notes associated with the change order
ApprovalThe formal approval statement for the change order, used in the Change Approval PDF and Change Order PDF. The text is pre-filled, and you can edit it.

Amounts tab

The Allocation Table shows one row for each allocation, with these columns:

ColumnWhat it shows
NameThe allocation name
Requested AmountThe value submitted by the contractor
Change AmountThe approved value recorded against the contract
Contract Line ItemThe contract line item the allocation relates to
BudgetThe budget the allocation relates to
TaxThe tax percentage

To download the allocation table, click Export in the toolbar, then choose an option:

Export optionWhat it does
Current ViewExports the table as displayed
All DataExports the complete dataset

Time Impact tab

SectionWhat it shows
Time ImpactThe Current Completion Date, Revised Completion Date, Days Approved, and Days Claimed
CommentsInternal-only comments related to the time impact assessment. You can add or view them here.

Documents tab

  1. Click + Add File, or drag and drop files directly onto the page, to upload documents.
  2. Use the Search bar to find specific files, or click Filter to narrow results.
  3. Click the Action menu next to any document to Download or Delete it.

For more details on managing documents, see How to Use the Documents Module.

Work with tables

Tables on this page, such as the Allocation Table on the Amounts tab, can be customized.

  • Click the action button on any column header to sort, pin, filter, or hide columns.
  • Use the toolbar to reset views, customize columns, apply filters, or export data.

Edit, download or delete a change order

From the Change Order Overview page:

ActionWhat it does
Back arrowReturns you to the Changes register
Edit Change (upper right)Opens the Update Change form so you can modify change order details
DownloadDownloads change order letters: Change Approval PDF, Change Order PDF, and Change Recommendation PDF
DeleteRemoves the change order. Change orders with payments cannot be deleted.

Troubleshooting and FAQs

What is the difference between Requested Amount and Change Amount?

Requested Amount is the value submitted by the contractor. Change Amount is the approved value recorded against the contract.

Who can see the Audit Log?

All users with access to the change order can view the Audit Log. It is read-only and cannot be edited.