How to View and Manage Variations in Variation Overview
Complete guide to navigating Variation Overview for construction project managers
Variation Overview is your central hub for managing a variation in Mastt. From here, you can review variation details and approval status, view cost allocations, assess time impacts, manage supporting documents, and track variation history, all in one place.
Before you start
A variation must already exist within a contract before you can view Variation Overview.
Open Variation Overview
- From the Mastt Home page, click a Project Tile to open your project.
- Click Cost in the left navigation bar.
- Click Variations in the top navigation bar to open the Variations register.
- Click the variation title to open Variation Overview.
Find your way around the tabs
Variation Overview organises variation information across five tabs.
| Tab | What it shows |
|---|---|
| Variation | The default view. Core details of the variation, including classification, approval status, and administrative fields. |
| Amounts | A detailed breakdown of all cost allocations included in the variation. |
| Time Impact | How the variation affects the project schedule. |
| Documents | All documents related to the variation. |
| Audit Log | A complete read-only history of all changes made to the variation, including user activity and timestamps, so you can track who made changes and when. |
Variation tab
Tip: Click the Contract Name below the variation title to go directly to the Contract Overview page.
| Section | What it shows |
|---|---|
| Overview | The Vendor, Variation Category, and Contract Variation Number assigned to the variation |
| Dates | Key dates, including Date Received, Date Approved, and Approved By |
| Additional Fields | Reference and tracking numbers such as Variation Number, Reference Number, Variation Approval Number, Clause, and other details |
| Recommendation | The recommendation notes associated with the variation |
| Approval | The formal approval statement certifying the contractor's variation in accordance with the Variation Approval or Order |
Amounts tab
The Allocation Table shows one row for each allocation, with these columns:
| Column | What it shows |
|---|---|
| Name | The allocation name |
| Requested Amount | The value submitted by the contractor |
| Variation Amount | The approved value recorded against the contract |
| Contract Line Item | The contract line item the allocation relates to |
| Budget | The budget the allocation relates to |
| Tax | The tax percentage |
To download the allocation table, click Export in the toolbar, then choose an option:
| Export option | What it does |
|---|---|
| Current View | Exports the table as displayed |
| All Data | Exports the complete dataset |
Time Impact tab
| Section | What it shows |
|---|---|
| Time Impact | The Current Completion Date, Revised Completion Date, Days Approved, and Days Claimed |
| Comments | Internal-only comments related to the time impact assessment. You can add or view them here. |
Documents tab
- Click + Add File, or drag and drop files directly onto the page, to upload documents.
- Use the Search bar to find specific files, or click Filter to narrow results.
- Click the Action menu next to any document to Download or Delete it.
For more details on managing documents, see How to Use the Documents Module.
Work with tables
All tabs display data in customisable table views.
- Click the action button on any column header to sort, pin, filter, or hide columns.
- Use the toolbar to reset views, customise columns, apply filters, or export data.
Edit, download or delete a variation
From the Variation Overview page:
| Action | What it does |
|---|---|
| Back arrow | Returns you to the Variations register |
| Edit Variation (upper right) | Opens the Update Variation form so you can modify variation details |
| Download | Exports variation reports |
| Delete | Removes the variation |
Troubleshooting and FAQs
What is the difference between Requested Amount and Variation Amount?
Requested Amount is the value submitted by the contractor. Variation Amount is the approved value recorded against the contract.
Who can see the Audit Log?
All users with access to the variation can view the Audit Log. It is read-only and cannot be edited.
Need help?
Contact Mastt Support for additional assistance with Variation Overview.